fbpx
Wednesday, January 22, 2025
Home Blog Page 44

HVAC Equipment – MEP Estimating Spreadsheet

Chapter #1 – HVAC Equipment – MEP Estimating Spreadsheet

You begin by opening your electronic estimating spreadsheet and entering the HVAC equipment listed on the equipment schedules which can be found on the mechanical drawings.

Mech Equip Schedule Metrics
Mech Equip Schedule Metrics

Record only the pertinent information that will help you figure labor hours for setting the equipment. Manufactures model numbers are of no use on the estimating spreadsheet, as they don’t provide any useful information for laboring the equipment.

EF1 Equip Schedule
EF1 on Equipment Schedule

After recording all of the equipment listed on the Equipment schedules, you’ll need to review the drawings to verify the quantity.

EF-1 Plan View
EF-1 Plan View

Some engineers will use the same equipment tag multiple times instead of changing the numerical value to indicate another piece of equipment that is the same; they will use the same equipment tag for multiple pieces of equipment that are the same make and model number. For instance, if the drawings have 30 of the same exhaust fan, the engineer may decide to use the equipment tag EF-1, instead of EF-1 through EF-30.

As shown below this engineer used the same tag (EF-1) for multiple locations, so don’t assume that there is only one as might be implied by the equipment schedule or the vendors quotation, always confirm by reviewing the drawings and details.

EF1 on Riser Diagram
EF1 on Riser Diagram

The above riser diagram is from a hotel where each bathroom had the same ceiling fan installed. The engineer in order to reduce the space required on the equipment schedule, listed the ceiling fan only once, which makes sense, but requires you to double check the drawings and vendor quotes for accuracy of quantity.

HVAC Equipment Tab on Estimating Spreadsheet

The purpose of the HVAC Equipment tab on your estimating spreadsheet is to allow a place to record vendor quotes (#8) and provide field installation labor (#5) for the equipment. Capacity (#3), weights and dimensions are more useful information, including the number of pieces the equipment comes in shipped from the manufacture or anything that would impact labor, including accessories (#4) that need to be field installed. Field installed items might include economizers, backdraft dampers, curbs, duct mounted smoke detectors and VFD’s.

HVAC Equipment Sheet
HVAC Equipment Sheet

Review Drawings

There are certain pieces of HVAC equipment or accessories that will not appear on the HVAC Equipment Schedule, depending on the design engineer’s standard of practice. Items such as the vibration isolation, air distribution, fire dampers, air separators, expansion tanks, water treatment, to name a few. This makes it necessary to review the drawings, details, control diagrams and specifications for unscheduled equipment and accessories.

Another factor that differs from one engineer to another is how they use equipment tags (#2 in above screen shot). Equipment tags like that shown below as EF-8 are used on the plans to identify which piece of HVAC equipment it refers to on the equipment schedule.

Equipment Tag
Equipment Tag

Owner Furnished Equipment

It’s common for some companies to have a national purchase agreement with major HVAC equipment manufactures in the hopes of saving the contractors markup fee, and negotiating a better price for national purchasing of a lot of equipment for various projects or stores owned. You will still need to list the owner furnished equipment as you will be responsible for unloading, rigging and setting of the equipment. Make sure to indicate on the estimating spreadsheet that the equipment is owner furnished.

HVAC Equipment Quantity (#6)

Enter the quantity of equipment (#6) into your Estimating Spreadsheet for each similar type of HVAC equipment you are itemizing. Remember not to rely on the equipment schedules for the quantity, but search through the drawings counting each piece as you mark them off. Vendors often make mistakes on quantities, so it’s important  that you do your count.

HVAC Equipment Description
HVAC Equipment Description

HVAC Equipment Tag (#2)

Put the equipment tags (#2) into the proper location on the estimating spreadsheet. Tags like EF-1 for Exhaust Fan #1, and AC-1 for Air Conditioner #1. Start with the most expensive equipment first or just lists them as you find them on the equipment schedules. Put a small check mark next to each of the equipment schedule titles to indicate that you have entered the information into the estimating spreadsheet.

HVAC Equipment Description (#1) & (#3)

Put a brief description of the equipment into the estimating spreadsheet. The title (#1) of the equipment is used first, such as Rooftop Heat Pumps, VAV Terminals, Air Handlers and the like. Underneath the title is where you’ll put the minimum information required to help you labor the item, information such as capacity (#3), weight and dimensions.

With an Air Conditioner you might put the Tons, CFM, and weight and list any accessories that require field labor such as economizers (#4). Indicate whether it sits on a roof curb (#4) or vibration isolation. Exhaust fans are listed by their type, such as Inline Fans, Ceiling Mounted Fans, Utility Fans, Roof Exhausters and the like, along with their CFM and weight.

Manufactures model numbers are not necessary because they give no useful information for laboring except for those pieces of HVAC equipment where model numbers indicate capacity.

HVAC Equipment Estimating SpreadSheet
HVAC Equipment Estimating SpreadSheet

Equipment Unit Labor Values (#5)

There are four categories of labor for HVAC equipment (#5) depending on the scope of work you intend to bid on. The options for labor units include Sheet Metal, HVAC Piping, Start and Test, and Balancing Labor. If you don’t do your own Air & Water Balancing or if mandated to be by a third party, then this cost will be covered by your Air & Water balancing subcontractor.

You put in the unit labor value for the quantity of one of these pieces of equipment and the total hours will be based on the quantity of this equipment. If you use 8 hours as your unit value for the rigging and setting of a utility fan and you have two (2) of them, then the spreadsheet will automatically multiply your unit value by the quantity to derive at a total labor of 16 hours for the sheet metal crew.

HVAC Equipment Vendor (#7)

List the company (#7) that is bidding on the piece of HVAC equipment identified by the equipment tags. These will most likely be the manufactures representative unless the manufacture sells direct to the contractor.

HVAC Equipment Quote (#8)

Here’s where you put the quotation amount (#8) that your vendors provide. The quotes are automatically compared for the lowest value, but can be overwritten by the user putting a value in the yellow highlighted plug box. Sometimes you don’t want the lowest bidder because their quote is incomplete or they’re not specified as an approved manufacture.

Plug or Quote (#9)

With the MEP Academy Estimating Spreadsheet you can choose to plug an amount (#9) for the HVAC equipment. This is useful when building budgets using the spreadsheet, or when you want to enter an amount different then the ones quoted by your vendors.

Low Bidder Automatically Selected (#10)

The MEP Academy Estimating Spreadsheet will automatically select the lowest bidder from amongst the quoted amounts (#8), unless you enter a different amount in the Plug or Quote box (#9).

Laboring the HVAC Equipment

You can labor the HVAC equipment after your sheet metal and piping takeoffs. The only step required in the beginning is to list the equipment on the Estimating Spreadsheet and notify your vendors. You can come back and labor the equipment at a later stage in the estimating process, after you have become more familiar with the project conditions. (See Chapter on Equipment Labor)

By taking off the equipment first you also get a good mental picture of the building layout and the systems being used. By the time you are done with your sheet metal and piping takeoff you will have a complete feel for the project, allowing you to better analyze the labor required to rig and set the equipment and determine any rentals you’ll need to accomplish this task.

HVAC Equipment Estimating Process

Step -1 (Notify Vendors & Subs)

Notify your vendors and subcontractors of the project and its bid date. Provide them with copies of the plans and specifications if they don’t already have copies. The use of Dropbox or other FTP sites where you can transfer large files to vendors or subcontractors will make the process much easier and faster than printing copies and sending them out in the mail.

Step – 2 (Record Equipment)

Type the list of equipment from the equipment schedule of the drawings into your estimating spreadsheet on the equipment tab, and any other equipment that is required.

Step – 3 (Labor Equipment)

After you have finished the takeoff of the trade materials such as Sheet Metal Ductwork or HVAC Piping, you can labor the equipment. Using historical data from previous projects or labor reference manuals such as SMACNA or MCAA, you can put labor for each line item into your equipment sheet of your estimating spreadsheet. You can also invite experienced office and field personnel to assist in evaluating the labor hours required for each item.

Step – 4 (Review Vendor Quotes)

Review vendor quotes and record them on your Estimating spreadsheet, choosing the lowest responsible price for that line item of equipment. This is when you review their quotation for compliance with the plans and specifications, taking note of anything they’re excluding. Reading the vendors exclusions is very important because it may still be part of your contractual obligation under the bid documents, or it could provide you notice of what you should exclude on your proposal.

Equipment Quotes
Equipment Quotes

Quick Parameter Checks (#11)

Your estimating spreadsheet should provide a means for verifying the cost metrics based on the typical benchmarks, such as CFM, Tons, HP (Horsepower) or cost each (#11). Whatever the metric used, this provides a quick check to ensure that you got the best price or that you haven’t made an input error. If you have one of the MEP Academy Estimating Spreadsheets than simply enter the values you want to measure and check to make sure that the cost metric makes sense.

Cost Metrics
Cost Metrics

Get the MEP Academy Estimating Spreadsheet here >>> MEP Academy Estimating Spreadsheet

Understanding the MEP Estimating Spreadsheet (Free Course)

Labor Rates

Chapter # 5 – Labor Rates

Union Labor Rates

In 2018, according to the US Government Bureau of Labor Statistics 10-1/2% of the wage and salary workers were union members. Non-union workers weekly paycheck is 82% of that of a union worker. Of course this varies by region and worker classification, as the largest union membership belongs in the educational (Teachers) and Protection Services (Police, Fire) sector. Most of the union works are in the public sector (33.9%) as opposed to the private sector (6.4%). Here is a sample of union labor rates for Sheet Metal Local Union 104 for San Francisco and surrounding areas in Northern California. Sheet Metal Local Union 104.

They can be a little confusing to read as each union includes or excludes different cost from their wage calculation and they use different acronyms. Below is an older version of the wage rate breakdown for an apprentice local 105 sheet metal worker. The apprentices hourly base rate is based on a percentage of the Journeymen’s wages. All wages are calculated as a percentage of the Journeymen as reflected in the first row which shows a percentage. As an example a 10th period apprentice earns 80% of what a Journeymen earns based on this wage sheet.

Included in the apprentices wages is the following;

  • Base wage (Hourly Taxable Wage). Here it indicates that they received a raise or increase over the previous period.
  • Savings Plan 10% (Its indicated that the savings plan is taxable)
  • 401(a) Plan (This is a mandatory participatory plan as opposed to a 401(k) which is voluntary.
  • Health Plan
  • Local Pension
  • Local Training J.A.T.C.. (This compensates the union for the expense of training)
  • National Training
  • National Pension
  • NEMI
  • SMOHIT – Sheet Metal Occupational Health Trust
  • LMCT – Labor Management Cooperation Trust
Union 105 Wage Rates
Example of Union Labor Rates

Labor Rates and Crew Size

With the MEP Academy Estimating Spreadsheet there are convenient labor tables for entering labor rates for various classes of workers whether union or non-union. Below is a screen shot from the spreadsheet where you choose how many workers you want at each skill level from a classified worker all the way to general foreman. Item # 1 are the different levels of workers and their pay rates for straight time, time and a half and double-time. By selecting how many of each worker type you need, the spreadsheet will calculate the crew rate shown as $48.00/Hour and indicated as item #2 below.

Sheet Metal Field Labor Rates
Sheet Metal Field Labor Rates

The layout of the labor table is similar to how sheet metal unions classify their workers, but any non-union company can set up the labor table according to their own levels of skilled workers.

The same applies for the Fabrication Shop if your company has one. Having these labor rate tables as part of your estimating spreadsheet provides for fast calculation of crew rates. It also provides a convenient location to keep the labor rate information used for a particular project.

Sheet Metal Shop Labor Rates
Sheet Metal Shop Labor Rates

Labor Agreements

Depending on the type of project you are bidding on, there may be requirements to comply with various labor agreements such as a PLA (Project Labor Agreement) or Davis Bacon.

Project Labor Agreement (PLA) 

Here is the definition of a Project Labor Agreement according to Wikipedia:

Project Labor Agreement (PLA), also known as a Community Workforce Agreement, is a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project. Before any workers are hired on the project, construction unions have bargaining rights to determine the wage rates and benefits of all employees working on the particular project and to agree to the provisions of the agreement. The terms of the agreement apply to all contractors and subcontractors who successfully bid on the project, and supersedes any existing collective bargaining agreements.

PLAs are used on both public and private projects, and their specific provisions may be tailored by the signatory parties to meet the needs of a particular project. The agreement may include provisions to prevent any strikes, lockouts, or other work stoppages for the length of the project. PLAs typically require that employees hired for the project are referred through union hiring halls, that nonunion workers pay union dues for the length of the project, and that the contractor follow union rules on pensions, work conditions and dispute resolution.

PLA’s can require non-union employees to pay union dues and follow union rules for the duration of the project. Be careful if the project you are bidding requires a PLA as this will increase the cost of your labor, especially if you are a non-union contractor with much lower rates than a typical union contractor.

Davis-Bacon Prevailing Wage Rates 

The Davis-Bacon Act, as amended, requires that each contract over $2,000 to which the United States or the District of Columbia is a party for the construction, alteration, or repair of public buildings or public works shall contain a clause setting forth the minimum wages to be paid to various classes of laborers and mechanics employed under the contract. Under the provisions of the Act, contractors or their subcontractors are to pay workers employed directly upon the site of the work no less than the locally prevailing wages and fringe benefits paid on projects of a similar character. The Davis-Bacon Act directs the Secretary of Labor to determine such local prevailing wage rates.

Davis Bacon Sheet Metal Wages
Davis Bacon Sheet Metal Wages

Davis-Bacon Wage Rates are established by the U.S. Department of Labor. The Davis-Bacon act was originally enacted in 1931 during the great depression. The purpose of the act was to establish fair wages on Federal construction projects. For any project where the Davis-Bacon act is applicable, the local wages will be published for the various classes of workers. The Davis-Bacon act applies to all subcontractors that your company hires.

Non-Union Labor Rates 

Non-Union Labor Rates are established by local conditions and the company hiring. The rates will vary by location depending on the availability of labor and the economic construction conditions. If you have a project that is bidding out of the area you normally build in, then you might have to pay subsistence for the travel and housing of any employee that you will use on that project. Labor rates will be different in Los Angeles, California compared to Derby, Kansas.

Fringe Benefits

Fringe Benefits are cost added to the base taxable wage rate and are usually found in Union contracts. These benefits might include retirement plans, health plans, local pensions, local training and national training funds. The Fringe benefits can add anywhere from 30% to 70% more of the base taxable wages. If you had a base taxable wage of $20.00, this could mean a total hourly wage packaged rate of anywhere from $26.00 to $34.00. The Unions publish their wage rates for their Union members, which includes a breakdown for the various classifications of workers from apprentice to general foremen.

Federal, State and Local Legal Requirements

There are mandatory legal requirements to make payments to various governmental agencies on behalf of the employees taxable hourly wage rate, in addition to the employer’s obligation for additional payments.

Federal Insurance Contributions Act (FICA)

The Federal Insurance Contributions Act (FICA) is a United States federal payroll contribution directed towards both employees and employers to fund Social Security and Medicare—federal programs that provide benefits for retirees, people with disabilities, and children of deceased workers.

Social Security tax amounts to 6,2% of wages up to a maximum $137,700, any wages above that amount aren’t subject to FICA taxes. The Federal government double dips on the Social Security tax by having the employee and employer both pay 6.2% of the employees’ wages, for a total tax of 12.4%. The employee pays 6.2% of their wage while the employer pays another 6.2% from their own funds. This may show as OASDI on your paycheck, which stands for “Old Age, Survivors and Disability Insurance”.

Medicare: Then the Federal Government deducts 1.45% from the employee’s paycheck and another 1.45% paid by the employer for a total of 2.9% for Medicare. The employee pays 1.45% from their paycheck and the employer 1.45% from their own funds. The Medicare portion has no maximum cap on the amount of income the employee makes that’s taxed.

This brings the total tax to the employee at 7.65%, made up of 6.2% for Social Security and 1.45% for Medicare. The percentage of the FICA taxes has stayed steady for a long time, it’s the Income limit that gets raised more often.

FICA Chart
FICA Chart

If you make more than $200,000 in 2020, then there is another 0.9% added to the Medicare portion for single filers.

Federal and State Unemployment Taxes

The Federal Unemployment Tax rate (FUTA) is currently 6% minus a 5.4% credit if you paid state unemployment taxes for a net tax of 0.6% of the first $7,000 of employee wages. The calculation equals a total tax of $42 for the year, figured as such; $7,000 x 0.6% = $42

The State Unemployment Insurance (SUI) tax rate varies by state and by the employer’s history of the number of employees laid off the previous year and the amount they pay their employees.

Workers Compensation

Workers Compensation payments vary by state, trade and by contractor’s accident rate. The lower your accident rate the better your workers compensation rate. This is why is imperative to have a safety program in order to educate your employees to work safe and to secure a lower workers compensation rate. There are some projects that will ask for your incident rate, and disqualify your company if your safety record is above a certain number.

These additional taxes are calculated against the employee’s taxable base rate, not including the fringe benefits.

Construction Laborers

Construction Laborers

Calculating Labor rates

Figuring out your labor rates should start with the going rate for the type of labor you need. If its a sheet metal worker with Journeymen experience then in your geographical area there will be an expected wage range.. If you are a Union company then you will abide by your local sheet metal unions negotiated rates per the bargaining agreement and that are published on a regular schedule. If you aren’t held to a bargaining agreement, but are left to set your own labor rates, then there are a few ways to go about figuring what to charge per hour for various skill levels and department functions.

Determining how much to charge per hour for various levels of skilled and unskilled workers can make the difference between losing a bid because your labor rates are too high and winning the bid but finding out that your labor rates don’t cover all your cost. First you need to develop a base rate like that shown in the union labor rate breakdown table above.

Foreman and Journeymen Vehicles

There are several methods that contractors use to cover the cost of your foremen and journeymen vehicles. You can add them to labor burden on top of the hourly rate or charge them to each job based on project duration. At some point accounting has to determine the method of cost recovery, so we just include it here so that you give it some thought.

Overtime and Shift Labor Rates

When required to work overtime or swing shift, certain values in your straight time labor rate will need to be adjusted to account for this additional requirement. The Fair Labor Standards Act (FLSA) is a Federal Law which establishes minimum wage, overtime pay, and which requires that you pay non-exempt employees 1-1/2 times their regular pay rate for all hours worked in excess of 40 for any work week. FLSA requires that you pay 1.5 times the regular rate of pay for all hours worked in excess of 8 per day and 40 per week for non-exempt employees.

The federal overtime provisions are contained in the Fair Labor Standards Act (FLSA). Unless exempt, employees covered by the Act must receive overtime pay for hours worked over 40 in a workweek at a rate not less than time and one-half their regular rates of pay. There is no limit in the Act on the number of hours employees aged 16 and older may work in any workweek. The Act does not require overtime pay for work on Saturdays, Sundays, holidays, or regular days of rest, unless overtime is worked on such days.

The FLSA applies to employment within any state of the United States, the District of Columbia or any territory or possession of the United States. An employee working in a foreign country is not protected by the FLSA even though the employer has its main office in the United States.

For some unions there is an extra premium for working shift hours, so if you work for a union company check the union agreement for overtime and shift hour payment requirements.

Union Concessions

Some of the sheet metal unions provide assistance for their union members when competing against non-union contractors on a competitive bid. These funds go by various names such as Market Recovery Funds, or Equality Funds. These funds help with the labor rate differences between union and non-union contractors in an attempt to level the playing field in the labor cost category. The Union may give a $20 dollar per hour reduction for their journeymen and $10 dollar reduction for their apprentices. The rates and concession amounts vary, and are only good for as long as the money in the fund is available.

Get the MEP Academy Estimating Spreadsheet here >>> MEP Academy Estimating Spreadsheet

Understanding the MEP Estimating Spreadsheet (Free Course)

General Conditions

Chapter #7 – General Conditions (MEP Estimating Spreadsheet)

We consider other cost to include general and special condition items, and indirect expenses, those items which are indirectly related to the construction of the project, but which are still required. We will cover the most common of these and how to figure them.

We like to have a separate form with many of the general and special conditions normally found on HVAC projects shown with their cost per unit already on the estimating sheet for quick reference. This will help you remember the most common items and the value that you use for them in each estimate.

General Conditions  – Management

Below is the top portion of the General Conditions tab of the MEP Academy estimating spreadsheet. Your company may use something different but the ideas and concepts of these cost are similar. It doesn’t matter where you locate these cost in your spreadsheet, so long as you have covered their cost if required.

We will cover the most commonly used general conditions for a new construction project.

General Conditions Management
General Conditions Management (MEP Academy Estimating Spreadsheet)

Project Managers

The project manager will oversee all aspects of the project including the project schedule and depending on the company; the project manager could be responsible for estimating, purchasing equipment and materials, and total oversight of the construction.

Project managers can manage many small projects or one large project. The cost of a project manager can be charged to each job for the time spent on that project. You can determine how much project management time you believe the project your bidding will need. Knowing what a project managers cost is allows you to prorate the expense for the duration of the project. You could also charge for the project manager as a percentage of the total cost of the project, such as 5%.

Project Engineers

Project engineers provide useful assistance to the project manager by doing some of the more mundane task of running a project, like preparing submittals, O&M manuals, chasing down drawing revisions and assisting in the overall running of the project. Project engineers are usually overseen by an experienced senior project manager and are more common on larger projects that require additional support for efficient execution of the project requirements.

Superintendent

The superintendent provides oversight of the labor force and coordinates with the project manager and subcontractors on labor aspects. A in company signatory to a union this would be the role of a union worker. For smaller companies this role might be carried out by the project manager.

Safety Managers

Depending on the size of the project and the requirements you could be required to provide a safety manager. The safety manager would be responsible for making sure that the workers follow the project safety requirements, such as wearing hardhats and googles, the proper use of equipment and tools, along with conducting safety tailgate meetings. The safety manager will be responsible for providing training of the field personnel, filing reports and recording any violations of the safety requirements.

Project Estimators

Depending on how your company is setup, the responsibility for pricing change-orders could be allocated to the project manager and his/her team or sent to the estimator located in the offsite company offices. Projects with a lot of change-orders should have the assistance of the estimating department so as not to stifle the project team. The estimating department is better setup to handle change-orders using their estimating software program.

Project/Administrative Assistants

Depending on the size of the project, additional jobsite office personnel maybe required to process all the correspondences and demands of a construction site that isn’t already covered by the project manager or project engineer.

Construction Office – Non-Reoccurring Cost

Non-reoccurring cost are those that will impact the project as a one-time cost as opposed to a monthly expense

construction office non-reoccurring-cost
construction office non-reoccurring-cost

Job Office Mobilization and Demobilization

This is the cost to have the office trailer brought in and setup, then torn down at the end of the project. This cost is independent of the monthly rental fee for the office trailer. Mobilization and demobilization also includes the cost of moving tools and equipment to the site for the execution of the scope of work, and then for the pickup of that equipment and tools at the end of the project.

Construction Office – Reoccurring Cost

Reoccurring cost are those that will impact the project on a monthly or regular basis, as opposed to a one time expense.

construction office reoccurring cost
Construction Office Reoccurring Cost – MEP Academy Estimating Spreadsheet

Job Office Rentals

Jobsite trailers or offices will be required on larger new construction projects as there is nowhere on site for you to conduct the administrative functions of the project. You will need an area to review drawings, and office space for your jobsite personnel.

Job Office Utilities

This is the cost incurred for the use of electrical power, water and gas. Often the general contractor will provide this at no charge, but it’s important to confirm who is paying for these cost.

Job Site Office Telephone/FAX

It’s possible that the project will require a landline and not just the cell phone of the jobsite personnel. You need to figure how long the project is going to last and the monthly cost for the service and usage fees if required.

Job Site Office Supplies

This might include paper for the copier, FAX machine or plotter, along with coffee, cups, sugar, creamer, water and miscellaneous supplies. Plug some value for the duration of the project based on your companies past experience for these type of office consumables.

Parking

Is there adequate onsite parking, or will you be required to rent offsite parking,? Will you be responsible for paying for onsite parking fees? Some of the Universities require the contractors to buy parking permits for the duration of any parking required by their vehicles.

It’s important to know if parking fees will be required to be paid by your company for any vehicles parked at the project site during the renovation or new construction. Area’s around large metropolitan cities, and at some of the Universities during school sessions are crowded and parking is limited. In certain cases you may be required to pay for your own parking.

Additionally, you may be required to bus workers in to the site if parking is provided remotely. Depending on your labor agreement, you may be responsible for getting field labor back to their cars by the end of the day, instead of at the gate or on the site of the project. This would require that you figure losing part of the work day to transporting your field labor.

Temporary Heating or Cooling

This requirement can often be found in the general requirements of the specifications. Add the cost to provide portable heaters or coolers as required. If the temporary system is large, then you will need to contact one of the equipment rental companies that specialize in providing and hooking up temporary systems.

Storage

You need to determine if there is an area on the project site that is allocated for your company to store materials as they are being staged for installation. Unless the project is being run under some form of Lean Construction where just in-time deliveries are being made on  the day the material will be used then some location on site will be required to store and stage material from. If there isn’t any space within the building to store building materials, then you’ll need to rent a lockable storage bin in order to store tools and materials.

Subsistence and Travel

Jobs that require your workers to work beyond certain boundaries as established by the unions, or for which the project is located out of town, and for those you will be sending will require subsistence.

Subsistence
Subsistence

Subsistence helps to compensate the employee for additional expenses incurred while away from home performing his/her duty as an employee. Depending on the location this could include a cost of living increase, as some cities and areas are more expensive than others. The employee may need to stay in a hotel or rent a temporary apartment for the duration of the project as it the distance would make it impossible to drive to the site and back daily. The renting of a vehicle may be required along with round trip airfare.

If you work for a union company then check the union agreement as to the daily subsistence rate for any employee that is required to travel beyond the allotted free zone. If the union employee uses their own vehicle make sure to check the union agreement for any required reimbursement of mileage driven to and from the project site. Most times the union employee is required to get to the project site at their own cost, unless it exceeds a certain distance from the designated union zone map epic center.

Other Cost

As-built Drawings

The requirement to provide as-built drawings or record drawings of the actual installation, should be stated in the specifications. This is almost certain to be a requirement on most projects, and even if it wasn’t a requirement, it is good business practice to provide the owner with a record of the actual installation. This could be as simple as marking with a red pencil or pen the actual routing of ducts and pipes including any size changes.

Liquidated Damages

You won’t put any cost for this in your estimate as the intent is to complete the project as defined in the specifications to avoid incurring a liquidated damages penalty. This might be found in the section entitled progress schedule, where it states that if the project goes past its scheduled completion date, there will be damages assessed. This is a penalty for delaying the completion  of the project, and is usually stated in so many dollars per day for every day that you pass the scheduled completion date.

Get a copy of the MEP Academy Estimating Spreadsheet here >> MEP Academy Estimating Spreadsheet

Understanding the MEP Estimating Spreadsheet (Free Course)

Sheet Metal Field Labor Productivity

Chapter #4 – Sheet Metal Field Labor Productivity

After your reports have finished running on the estimating computer software program its time to review the field labor. If you don’t have a computer estimating software program then your all your field labor numbers would be generated using Excel or some other spreadsheet totaling software. Hopefully your estimating software has the capability to breakdown the labor reports for easy analyses.

We will want to look at the labor productivity, meaning how many linear feet of ductwork is being installed per man-day (LF/MD) as one of the methods of labor analysis, or linear feet per hour (LF/HR) if you want to look at it in a micro sense. A man-day is equivalent to an 8-hour day.

Another method of labor analysis is hours/piece (Hrs/Pc) and pounds/hour (Lbs/Hr). When we took the sheet metal off we separated our takeoff into different zones and systems. At this point we would analyze each zone and system separately.

There is no better way to review the productivity of your project, except to go through it line by line as grouped per your System and Zone descriptions. This will help those in the estimating review to build the job in their head, giving everyone involved a good sense of the project. If you apply a factor overall to everything, no one will fully grasp the project as deeply as a thorough review would allow. Some companies do just that—they apply one factor to all the labor based on the type of project.

We will first cover some of the factors that affect productivity. This is often one of the most difficult undertakings of an estimator, the analysis and adjustment of labor for non-typical conditions. If using a computer estimating program with SMACNA labor units, then you would be adjusting from a 1.0 of SMACNA labor.

Measuring Labor Productivity

This is one of the main duties of the sheet metal estimator, as it has the greatest impact on cost. Labor proposes the highest risk to the contractor, as it is one of the greatest variables. The cost for other aspects of the bid, such as material, equipment and subcontracts shouldn’t vary much from their original bid time cost, unless an error was made.

But labor will vary from your assumptions at bid time about how productive the field labor would be able to install the required equipment and material. So it is labor that really needs to be understood in order to provide accurate estimate that will return a reasonable profit for the owners.

SMACNA Labor Benchmark

There are various organizations that publish labor productivity values for the HVAC Sheet Metal industry including SMACNA, the Sheet Metal and Air Conditioning National Association. There are various factors affecting the productivity of labor from some baseline, or benchmark standard. Each project presents various challenges based on differing site conditions. Labor needs to be adjusted from the standard benchmark labor units to match the specifics of the project under consideration.

Most often labor is the riskiest portion of the estimate because of the assumptions made on the productivity that the project is assumed to be able to redeem. SMACNA provides three progressive categories of labor risk, “Normal”, “Difficult”, and “Very Difficult”. As the conditions worsen, the corresponding labor cost will increase. If you are bidding a retrofit project, one in where you are working in an existing building, then SMACNA considers all remodels to be categorized as either “Difficult” or “Very Difficult”.

SMACNA Labor Tables (Database)

If you are using the SMACNA Reference Manual for Labor Units for your field labor productivity then you will apply a factor to align the SMACNA labor with your field labor feedback (Historical Data), if your company maintains such information. SMACNA labor tables were original assembled from a survey of over 300 member firms from the United States and Canada.

The labor units contain 138 tables for the fabrication and installation unit labor values for the installation of ductwork, fittings, hangers, equipment and accessories. Labor units are available in pounds per hour, or hours per piece, in addition to labor for equipment based on the size of the HVAC equipment.

The SMACNA labor units exclude engineering, supervision, field layout (Detailing) or non-standard construction.

You can use the SMACNA labor units that are embedded in your estimating software if you have one, or you could purchase the SMACNA labor units Excel version, that allows you to adjust values using their spreadsheet. The electronic Excel spreadsheet allows you to rate your project in 30 different difficulty categories in an effort to provide you with the difficulty factor of your project compared to a standard project. There are three project difficulty ratings based on the information you enter for your project, indicated as “normal”, “difficult”, or “very difficult.”

Labor Feedback

The best way to determine how much labor is required for a particular task of work, is to review historical data, that is what it took your companies field crew in hours to perform similar work that has already been completed.

If you are fortunate enough to work for a company that tracks their labor, then you will have a labor database to review when assembling an estimate. The database accumulated from labor feedback will give you a reference for how long it takes to install various materials and equipment, depending on the sophistication and accurate tracking and reporting of the labor spent.

Historical data should be used as a guide for your current project, but not without serious consideration for the differences in the respective projects. Just as SMACNA rates the different categories of labor according to their difficulty, you must know under what conditions your historical database reference project labor was installed under. Understanding what effects labor is the first place to begin before any adjustments up or down from a benchmark labor database is performed.

Industry Labor Database vs Historical Data

There are two main ways to bid labor on a project. The first is to use an industry labor database, and the other is to use some form of historical labor feedback from completed projects. The third way is to use a hybrid of the two. Do your takeoff using the industry standard database, such as SMACNA labor units, and then adjust the productivity according to your historical labor.

The most accurate labor productivity is going to be based on the feedback you received from the field on jobs completed that are similar to the one you are currently proposing, making adjustment for any differences. Let’s look at a few ways to record and adjust labor in the field.

Sheet Metal Labor Productivity Units

There are several methods for analyzing labor productivity for any project. You need to find one that you are comfortable with and that matches the specifics of your company. We will cover four methods of measuring labor productivity.

Duct hung in Wood Structure
Duct hung in Wood Structure

Labor can be measured in LF/MD (linear feet per man day), which means that so many feet of duct can be installed in an 8 hour period, the same unit can be defined as LF/HR (linear feet per hour), which means how many feet can be installed in one hour.

Some contractors like to look at LBS/HR, which means how many pounds of sheet metal that can be installed in an hour. And then there is the HRS/PC (hours per piece), which is defined as how many hours it takes to install a piece of duct or fitting.

MD = 8 hours

  1. LF/MD = Linear feet per man day
  2. LF/HR = Linear feet per hour
  3. LBS/HR = Pounds per hour
  4. HRS/PC = Hours per piece

Linear Feet Per Hour (LF/HR) & Linear Feet Per Man Day (LF/MD)

Ft/MD (Feet per Man Day) is used as a measurement of the labor productivity for a certain ductwork system. If your labor feedback from previous projects indicates that you can install rectangular main ducts at 25 LF/MD (linear feet per man day), then you would apply this productivity factor to the total linear feet of main ductwork you have for the current project if the duct sizes and fitting quantity are similar.

Then you would add any of the labor corrections factors that are applicable for the current project. For example let’s say you have 200 linear feet of main ductwork. You would take the 200 feet and divide it by the historical labor feedback of 25 LF/MD which would equal 8 man days or 64 hours (200 200 LF/ (25LF/MD) = 8 Man Days or 64 Hours.

To this you would adjust for any factors effecting labor. (See course section on “Factors Affecting Field Labor.”) If you receive your ductwork from the fabrication shop KD (knocked down – unassembled), then you will have to add the time it takes to assemble the ductwork on site, which is separate from the time it takes to install the ductwork.

Additionally, if you had 3,000 feet of ductwork and fittings, and your benchmark labor database determined that it would take 800 hours to install this ductwork & fittings, this would equate to 30 LF/MD (30 linear feet per man day)

LF/HR = 3,000 Ft / 800 Hours = 3.75 LF/HR (Linear feet per hour)

To get to linear feet per man day, just multiple by 8 hours in a day.

LF/MD = (3,000 Ft / 800 hours) x 8 Hours/Day = 30 LF/MD

3.75 LF/HR = 30 LF/MD (These two represent the same labor productivity factor)

Pounds per Hour (LBS/HR)

This method is available in the SMACNA labor database as an option for labor analysis. Differing productivity values (Lbs/Hr) are used for different size and gauges of ductwork. As ducts get larger or their gauges get heavier, the duct and fittings increase in weight (pounds).

Example: if you had a 10 feet of 12” x 12” duct at 26 ga, this would equal

STEP-1 Remember that stretch-out is derived by unfolding the duct from a four sided box into a flat piece of metal, so that a 12” x 12” duct unfolded would look like this;

12” + 12” + 12” + 12” = 48” or 4 feet.

STEP-2 Determine how many pounds of sheet metal you have. We have sheet metal ductwork that is 10 feet long by 4 feet wide (stretch-out), which equates to 40 FT2.

10 feet x 4 feet = 40 FT2

STEP-3 Convert the 40 FT2 into pounds by using the conversions value for 26 gauge (0.906 LBS/FT2) galvanized sheet metal, which is.

40 FT2 x 0.906 = 36.24 LBS

STEP-4 Apply your productivity factor (LBS/HR) to the total pounds of duct at this size. Per SMACNA the productivity at this size and gauge is 24.70 LBS/HR. This would calculate out as

36.24 LBS / (24.7 LBS/HR) = 1.46 Hours

The pounds per hour labor productivity factor is the most difficult to visualize. The difficulty comes from the fact that the same five-foot piece of ductwork has different weights at the different gauges, and it’s difficult to tell how much duct weight by looking at hit. It’s easier to count how many pieces have been installed or how many linear feet. What does 300 pounds a day look like, as compared to 25 feet a man-day? It’s easier to visualize the quantity of feet or pieces.

How does the Foreman determine at the end of the day how many pounds the crew has installed? We strongly recommend that you don’t use this method, but choose one of the other labor productivity measuring factors.

Labor Productivity Calculations
Labor Productivity Calculations

Hours per Piece (HRS/PC)

This is the second method available in the SMACNA labor database as an option for field labor analysis. Differing productivity values (HRS/PC) are used for different stretch-out sizes (perimeter). Using the same  10 foot 12” x 12” duct from above, and assuming that we are using 5 foot joint lengths, would mean that we have two (2) 5-foot sections of duct. Using the SMACNA table for low pressure galvanized straight duct with a 4 foot stretch-out and the 26 ga column, we get 0.8611 HRS/PC.

2 pieces x 0.8611 HRS/PC = 1.72 Hours

Using the same 12’ x 12” section of ductwork we can see that depending on which units of labor you use, you derive at different totals. For the LBS/HR unit labor, you get 1.46 hours, while the HRS/PC method gives you 1.72 hours based on the SMACNA database.

Once you decide on which units of labor you will use, then you should stick with it, so that you can develop a sense of familiarity.

Some prefer to use the hours per piece as a means of measuring their labor productivity in the field. This is somewhat similar to the feet per man-day in that if you know the length of each piece of duct

Practice Calculations

Calculate the LF/MD using the following information: (Answers below at end of this course)

Let’s assume your estimating software or manual takeoff has provided you with the following data;

  1. Rectangular Duct = 1,200 feet and 320 hours. (What is the linear feet per man-day?)
  2. Round Duct = 1,800 feet and 240 hours. (What is the linear feet per man-day?)
  3. Adjust the labor productivity to 25 LF/MD for question #1. What are the new hours?
  4. Adjust the labor productivity to 50 LF/MD for question #2. What are the new hours?

Military Project Labor Productivity

This chart is derived from the U.S. Military and shows what they assume it takes to put in rectangular and round sheet metal ducts based on their standard project assumptions. You should establish something similar for your company based on labor feedback from a sample of various project types. This will help you establish your standard benchmark for labor by which all future project labor would be adjusted from, such as SMACNA developed for its membership.

Military Sheet Metal Productivity-Chart
Military Sheet Metal Productivity-Chart

U.S. Military Sheet Metal Labor Productivity Values

Which Labor Unit Method is Best?

We prefer the LF/MD or LF/HR method of labor productivity analysis because it’s visually represented better than the others. For example, if you were to visit a jobsite to review the ductwork that has been installed, and you’re looking at a section of ductwork hanging in the buildings first floor ceiling, could you tell how many pounds of metal it is? This would require you to do some mental gymnastics, or some quick calculation as to what gauge and size the duct was in order to calculate the weight, and then divide by the productivity factor.

Productivity factors using weight in our opinion is not a good labor unit for visually inclined estimators and project managers. There must be a reason why the military uses LF/MD & LF/HR, and that is, it represents an easier way to visualize what has been installed, and for setting a benchmark for field productivity performance.

Proper Takeoff Techniques

Labor productivity factors will vary based on job site conditions as discussed above, but with everything being equal, productivity will also differ based on duct size. There is no way for a crew to install a 64” x 36” section of duct at the same productivity as a section of 12” x 12” duct. So, for this reason your adjustment factors need to be broken down as shown in the military labor unit schedule.

Benchmarking Labor Productivity Performance

When the project is under construction and ductwork begins to get installed, the project management team should begin measuring weekly what was installed and the amount of hours expended for the portion of the project related to the Sheetmetal ductwork. This will let them know if they are hitting their estimated productivity goals.

This is done by taking a fresh new set of drawings out to the jobsite for benchmarking the performance that occurs each week. Each week the ductwork on the drawings that has been installed gets colored on the drawings, documenting the progress of the project. Back at the office, the ductwork that was colored in for that week gets taken off to determine how many linear feet of ductwork was installed compared to how many hours were charged for installing the ductwork that week.

If the sheet metal crew had installed 900 feet of ductwork and they used a six person crew for a week, then the actual productivity would be as follows;

6 Crew Members x 40 Hours/Wk = 240 Hours spent

900 Feet / 240 Hrs = 3.75 LF/HR or 30 LF/MD

Correction/Adjustment Factors

The correction factors shown below are used to adjust a base unit of labor that is considered normal conditions. The correction factors then would adjust this normal condition base unit for any conditions out of the norm. If you review MCA and SMACNA labor units their method is similarly based on a standard unit of measure for which unusual conditions are adjusted. Labor productivity will vary by building type and projects, and may require more or less than the benchmark database labor.

These adjustment factors are just suggestion, and are not hard percentages that you should rely on. All labor adjustments should be something that is derived from experience and historical data that your company tracks. This applies to all the adjustment factors shown in this course.

Height of Installed Ductwork: Anytime your ductwork is hung above 10 to 13 feet you will need to adjust for the increased height. If the field labor can’t work off ladders then you will need some type of scaffold or scissor lift. Add 2% to 10% for ducts hung 11’ to 15’: add 10% to 20% for ducts hung from 16’ to 20’, and so on:

Labor Correction Factor for Ductwork Height
Labor Correction Factor for Ductwork Height

Quantity of Floors: As mentioned above the quantity of floors will have an impact on your labor when the quantity of floors exceeds three. This is the additional time it takes to reach higher and higher floors in the building.

Labor Correction Factor for Quantity of Floors
Labor Correction Factor for Quantity of Floors

Weather Conditions

We all know what it’s like to work in excessively hot or cold weather. Workers just don’t perform at the same productivity levels as they do under normal weather conditions. You can get more done in a nice controlled environment than if you had to work on a cold concrete floor on the 10 floor of a new high-rise that has no walls installed yet, and the cold wind is blowing through the building.

If the project will be built during extreme weather conditions, than you should adjust for a loss of productivity due to the weather. The question is what would the weather conditions be during the duration of the project?

Extremes of either hot or cold weather will result in a loss of labor productivity. Humans don’t function as well when the temperature of the ambient air is outside their comfort zone. This goes for working in areas such as hot boiler rooms or equipment rooms where the temperature is outside the normal range for human comfort.

Temperature Factor on Labor Productivity
Temperature Factor on Labor Productivity

Field Labor Feedback

If you have been in business for any period of time you have established some historical data on the field time required to install ductwork, equipment and accessories. From this historical data, you can project what kind of productivity you should get for the current, similar job. If the jobs are not similar, then you must adjust the productivity up or down depending on the current projects relative ease or difficulty compared to your historical project.

There is no better measure of productivity than your own historical data, but each job will still be unique and should be carefully scrutinized for those areas where productivity could be affected.

Answers to Practice Calculations

  1. 30 LF/MD (1,200 LF/320 hours) x 8 hrs/day)
  2. 60 LF/MD = (1,800 LF/240 hours) x 8 hrs/day
  3. 384 Hours (1,200 LF/ 25LF/MD) x 8
  4. 288 Hours (1,800 LF/ 50LF/MD) x 8

Sheet Metal Field Installation Course (Free)